Segment C

FPID Number: 421707-4
From South of Miramar Parkway to South of Sheridan Street

Approximate Length: 3.6 Miles
Cost: $85 Million
Construction Start Date: June 2014
Anticipated Completion Date: Winter 2017
CEI: A&PCT Engineers
Design-Build: Wantman Group
Contractor: Ranger Construction
 
Affected Municipalities:
     Pembroke Pines
     Miramar

Segment Overview

Segment C begins South of the Miramar Parkway to South of Sheridan Street. Work includes:

  • Constructing Express Lanes in the existing median on I-75, two northbound and two southbound lanes
  • Constructing entrance and exit access points to the Express Lanes
  • Constructing a bridge over I-75 at Pembroke Road
  • Reconstructing the bridge and interchange at Miramar Parkway
  • Installing sound barrier walls adjacent to the following communities:
    • Villas at Nautica
    • Windsor at Miramar
    • Cobblestone Townhomes
    • Towngate
  • Adding new drainage, signage, lighting and landscaping
  • Installing additional Traffic Cameras, Dynamic Message Signs and Toll Gantries