FPID Number: 421707-5
From South of Sheridan Street to North of Griffin Road

Approximate Length: 3.7 Miles
Cost: $80 Million
Construction Start Date: September 2014
Anticipated Completion Date: Winter 2017
CEI: Target Engineering Group, Inc.
Design-Build: Wantman Group
Contractor: Ranger Construction

Affected Municipalities:
    Davie
    Southwest Ranches
    Cooper City
    Pembroke Pines

Segment Overview

The Segment D portion of the 75 Express Lanes Project begins South of Sheridan Street to North of Griffin Road. Work includes:

  • Constructing Express Lanes in the existing median on I-75, two northbound and two southbound lanes
  • Constructing entrance and exit access points to the Express Lanes
  • Widening the Sheridan Street bridge over I-75
  • Reconstructing the Sheridan Street Interchange
  • Installing sound barrier walls adjacent to the following communities:
    • Towngate
    • Sheridan Glen
    • The Crossbow
    • Falcon's Lea
    • Waverly Hundred
    • Hawkes Bluff
    • Waterford
    • Ivanhoe Estates
    • Chelsea
  • Adding new drainage, signage, lighting and landscaping
  • Installing additional Traffic Cameras, Dynamic Message Signs and Toll Gantries